Duration: 19 weeks (16 weeks + 3 weeks delay)
| Task Name | Duration | Start Date | Finish Date | Notes | |
|---|---|---|---|---|---|
| 1 | Iteration 1 | 4 weeks | Mon 07/10/2006 | Fri 08/4/2006 | |
| 2 | Fix Approved Defects for 4.2.1 | 3 week | Mon 07/10/2006 | Fri 07/28/2006 | Done |
| 3 | Test and fix (sev 1 and sev 2) | 1 week | Mon 07/31/2006 | Fri 08/04/2006 | Done |
| 4 | Create CVS Branch for 4.2.1 | --- | Mon 08/07/2006 | Fri 08/07/2006 | Done |
| 5 | Iteration 2 (4.3 only) | 7 weeks | Mon 08/07/2006 | Fri 09/22/2006 | No stable build produced |
| 6 | Design/Code 4.3 Features | 5 week | Mon 08/07/2006 | Fri 09/08/2006 | Done |
| 7 | 4.3 Feature freeze | --- | Fri 09/08/2006 | Fri 09/08/2006 | Done on 9/19 |
| 8 | Test and fix (sev 1 and sev 2) | 1 week | Mon 09/11/2006 | Fri 09/15/2006 | Actual duration: 9/20 - 10/9 (overlapped with 4.2.1 testing) |
| 9 | Test and fix (STOP SHIP Only) | 1 week | Mon 09/18/2006 | Fri 09/29/2006 | Actual duration: 10/10 - 10/20 |
| 10 | 4.2.1 Release Testing | 2 week | Mon 09/11/2006 | Fri 09/29/2006 | |
| 11 | Test Pass 2 | 1 week | Mon 09/11/2006 | Fri 09/15/2006 | Done |
| 12 | Test Pass 3 | 1 week | Mon 09/18/2006 | Fri 09/22/2006 | Done |
| 13 | Contribute GA bits to Callisto | --- | Web 09/27/2006 | Web 09/27/2006 | Done. Release bits published to update and download sites |
| 14 | General Availability of TPTP 4.2.1 | --- | Fri 09/29/2006 | Fri 09/29/2006 | Announcement will be made |
| 15 | Iteration 3 (4.3 only) | 4 weeks | Fri 10/20/2006 | Fri 11/17/2006 | |
| 16 | Fix defects with PL approval | 2 weeks | Mon 10/02/2006 | Fri 11/03/2006 | Defects pre-approved by PMC/PG |
| 17 | Test and fix (STOP SHIP only) | 2 weeks | Mon 11/06/2006 | Fri 11/17/2006 | Need PL and PMC/PG approval |
| 18 | General Availability of TPTP 4.3 | --- | Mon 12/04/2006 | Mon 12/04/2006 |
Lasted Updated on 10/23/2006 09:20 PM Pacific Time