Duration: 25 weeks
Eclipse 3.2 Plan
| Task Name | Duration | Start Date | Finish Date | Notes | |
|---|---|---|---|---|---|
| 1 | Iteration 1 | 7 weeks | Mon 01/09/2006 | Fri 02/24/2006 | |
| 2 | Design | 1 week | Mon 01/09/2006 | Fri 01/13/2006 | |
| 3 | PII Drop 1 | --- | Wed 01/11/2006 | Wed 01/11/2006 | Drop will be made early Thursday morning |
| 4 | Code | 4 weeks | Mon 01/16/2006 | Fri 02/10/2006 | |
| 5 | Test and fix (sev 1 and sev 2) | 1 week | Mon 02/13/2006 | Fri 02/17/2006 | |
| 6 | PII Drop 2 | --- | Wed 02/15/2006 | Wed 02/15/2006 | Drop will be made early Thursday morning |
| 7 | Eclipse Project API Freeze | --- | Fri 02/17/2006 | Fri 02/17/2006 | |
| 8 | Test and fix (sev 3 and sev 4) | 1 week | Mon 02/20/2006 | Fri 02/24/2006 | |
| 9 | Stable build - API freeze; Callisto M5 | --- | Fri 02/24/2006 | Fri 02/24/2006 | |
| 10 | PII Drop 3 | --- | Wed 03/01/2006 | Wed 03/01/2006 | Drop will be made early Thursday morning |
| 11 | Enablement test cases due | --- | Wed 03/15/2006 | Wed 03/15/2006 | Deliver the tests by 9 AM EST How to write an enablement test case Where to deliver the enablement tests |
| 12 | Iteration 2 | 7 weeks | Mon 02/27/2006 | Fri 04/14/2006 | |
| 13 | Design | 1 week | Mon 02/27/2006 | Fri 03/03/2006 | |
| 14 | Enablement testing | 5 weeks | Mon 03/06/2006 | Fri 04/07/2006 | |
| 15 | Code | 4 weeks | Mon 03/06/2006 | Fri 03/31/2006 | |
| 16 | PII Drop 4 | --- | Wed 03/29/2006 | Wed 03/29/2006 | Drop will be made early Thursday morning |
| 17 | Doc Drop 1 | --- | Wed 03/29/2006 | Wed 03/29/2006 | Drop will be made early Thursday morning |
| 18 | Feature freeze | --- | Fri 03/31/2006 | Fri 03/31/2006 | |
| 19 | PII change approval starts | --- | Fri 03/31/2006 | Fri 03/31/2006 | |
| 20 | Eclipse Project Feature Complete | --- | Fri 03/31/2006 | Fri 03/31/2006 | |
| 21 | Test and fix (sev 1 and sev 2) | 1 week | Mon 04/03/2006 | Fri 04/07/2006 | |
| 22 | Translation Verification Test (TVT) cases due | --- | Fri 04/07/2006 | Fri 04/07/2006 | Drop will be made Friday. Please have all tests in CVS by 9 AM EST. How to write a translation test case Where to deliver the translation tests |
| 23 | PII Drop 5 | --- | Wed 04/12/2006 | Wed 04/12/2006 | Drop will be made early Thursday morning |
| 24 | PII freeze | --- | Wed 04/12/2006 | Wed 04/12/2006 | |
| 25 | Test and fix (sev 3 and sev 4) | 1 week | Mon 04/10/2006 | Fri 04/14/2006 | Overlaps the design week of iteration 3 |
| 26 | Stable build - UI freeze; Callisto RC0 | --- | Fri 04/14/2006 | Fri 04/14/2006 | |
| 27 | Iteration 3 | 6 weeks | Mon 04/10/2006 | Fri 05/26/2006 | |
| 28 | Design | 1 week | Mon 04/10/2006 | Fri 04/14/2006 | Overlaps the test week of iteration 2 |
| 29 | Code | 4 weeks | Mon 04/17/2006 | Fri 05/12/2006 | |
| 30 | PII Drop 6 | --- | Wed 04/19/2006 | Wed 04/19/2006 | |
| 31 | Callisto RC1 | --- | Fri 04/28/2006 | Fri 04/28/2006 | |
| 32 | Callisto RC2 | --- | Fri 05/12/2006 | Fri 05/12/2006 | |
| 33 | Translation Verification Test (TVT) | 6 weeks | Mon 05/08/2006 | Fri 06/16/2006 | |
| 34 | Doc Drop 2 | --- | Wed 05/10/2006 | Wed 05/10/2006 | Drop will be made early Thursday morning |
| 35 | Test and fix (sev 1 and sev 2) | 1 week | Mon 05/15/2006 | Fri 05/19/2006 | |
| 36 | Test and fix (sev 3 and sev 4) | 1 week | Mon 05/22/2006 | Fri 05/26/2006 | |
| 37 | Iteration 4 | 5 weeks | Mon 05/29/2006 | Fri 06/30/2006 | |
| 38 | Test and fix (STOP SHIP only) | 5 weeks | Mon 05/29/2006 | Fri 06/30/2006 | |
| 39 | Stable build - Callisto RC3 | --- | Fri 06/02/2006 | Fri 06/02/2006 | |
| 40 | Doc Drop 3 | --- | Wed 06/07/2006 | Wed 06/07/2006 | Drop will be made early Thursday morning |
| 41 | Doc freeze (excluding doc delivered only on the web) | --- | Wed 06/07/2006 | Wed 06/07/2006 | |
| 42 | Callisto RC6 | --- | Wed 06/28/2006 | Wed 06/28/2006 | |
| 43 | General Availability, English only | --- | Fri 06/30/2006 | ||
| 44 | General Availability, Translation | --- | Aug 06 (tentative) |