Duration: 25 weeks
Eclipse 3.2 Plan

Task Name Duration Start Date Finish Date Notes
1 Iteration 1 7 weeks Mon 01/09/2006 Fri 02/24/2006  
2 Design 1 week Mon 01/09/2006 Fri 01/13/2006  
3 PII Drop 1 --- Wed 01/11/2006 Wed 01/11/2006 Drop will be made early Thursday morning
4 Code 4 weeks Mon 01/16/2006 Fri 02/10/2006  
5 Test and fix (sev 1 and sev 2) 1 week Mon 02/13/2006 Fri 02/17/2006  
6 PII Drop 2 --- Wed 02/15/2006 Wed 02/15/2006 Drop will be made early Thursday morning
7 Eclipse Project API Freeze --- Fri 02/17/2006 Fri 02/17/2006  
8 Test and fix (sev 3 and sev 4) 1 week Mon 02/20/2006 Fri 02/24/2006  
9 Stable build - API freeze; Callisto M5 --- Fri 02/24/2006 Fri 02/24/2006  
10PII Drop 3---Wed 03/01/2006Wed 03/01/2006Drop will be made early Thursday morning
11Enablement test cases due---Wed 03/15/2006Wed 03/15/2006Deliver the tests by 9 AM EST
How to write an enablement test case
Where to deliver the enablement tests
12 Iteration 2 7 weeks Mon 02/27/2006 Fri 04/14/2006  
13 Design 1 week Mon 02/27/2006 Fri 03/03/2006  
14 Enablement testing  5 weeks Mon 03/06/2006 Fri 04/07/2006  
15 Code 4 weeks Mon 03/06/2006 Fri 03/31/2006  
16 PII Drop 4 --- Wed 03/29/2006 Wed 03/29/2006 Drop will be made early Thursday morning
17 Doc Drop 1 --- Wed 03/29/2006 Wed 03/29/2006 Drop will be made early Thursday morning
18 Feature freeze --- Fri 03/31/2006 Fri 03/31/2006  
19 PII change approval starts --- Fri 03/31/2006 Fri 03/31/2006  
20 Eclipse Project Feature Complete --- Fri 03/31/2006 Fri 03/31/2006  
21 Test and fix (sev 1 and sev 2) 1 week Mon 04/03/2006 Fri 04/07/2006  
22 Translation Verification Test (TVT) cases due --- Fri 04/07/2006 Fri 04/07/2006 Drop will be made Friday. Please have all tests in CVS by 9 AM EST.
How to write a translation test case
Where to deliver the translation tests
23PII Drop 5---Wed 04/12/2006Wed 04/12/2006Drop will be made early Thursday morning
24PII freeze---Wed 04/12/2006Wed 04/12/2006 
25 Test and fix (sev 3 and sev 4) 1 week Mon 04/10/2006 Fri 04/14/2006 Overlaps the design week of iteration 3
26Stable build - UI freeze; Callisto RC0---Fri 04/14/2006Fri 04/14/2006 
27 Iteration 3 6 weeks Mon 04/10/2006 Fri 05/26/2006  
28 Design 1 week Mon 04/10/2006 Fri 04/14/2006 Overlaps the test week of iteration 2
29 Code 4 weeks Mon 04/17/2006 Fri 05/12/2006  
30 PII Drop 6 --- Wed 04/19/2006 Wed 04/19/2006  
31 Callisto RC1 --- Fri 04/28/2006 Fri 04/28/2006  
32 Callisto RC2 --- Fri 05/12/2006 Fri 05/12/2006  
33 Translation Verification Test (TVT) 6 weeks Mon 05/08/2006 Fri 06/16/2006  
34 Doc Drop 2 --- Wed 05/10/2006 Wed 05/10/2006 Drop will be made early Thursday morning
35 Test and fix (sev 1 and sev 2) 1 week Mon 05/15/2006 Fri 05/19/2006  
36 Test and fix (sev 3 and sev 4) 1 week Mon 05/22/2006 Fri 05/26/2006  
37 Iteration 4 5 weeks Mon 05/29/2006 Fri 06/30/2006  
38 Test and fix (STOP SHIP only) 5 weeks Mon 05/29/2006 Fri 06/30/2006  
39 Stable build - Callisto RC3 --- Fri 06/02/2006 Fri 06/02/2006  
40 Doc Drop 3 --- Wed 06/07/2006 Wed 06/07/2006 Drop will be made early Thursday morning
41 Doc freeze (excluding doc delivered only on the web) --- Wed 06/07/2006 Wed 06/07/2006  
42 Callisto RC6 --- Wed 06/28/2006 Wed 06/28/2006  
43 General Availability, English only --- Fri 06/30/2006    
44 General Availability, Translation --- Aug 06 (tentative)