TPTP Project Schedule
 
 
 
Project Start:
Project Finish:
Mon 7/11/05
Mon 11/14/05
 
TPTP 4.1  
ID
Task Name
DurationStart_DateFinish_DateNotes
1
TPTP 4.1
85 days?Mon 7/18/05Fri 11/11/05 
2
Iteration 1
35 days?Mon 7/18/05Fri 9/2/05 
3
Design
5 days?Mon 7/18/05Fri 7/22/05 
4
Code
20 days?Mon 7/25/05Fri 8/19/05 
5
Test & Fix (sev 1 & 2)
5 days?Mon 8/22/05Fri 8/26/05 
6
Test & Fix (sev 3 & 4)
5 days?Mon 8/29/05Fri 9/2/05 
7
Iteration 2
35 days?Mon 9/5/05Fri 10/21/05 
8
Design
5 days?Mon 9/5/05Fri 9/9/05 
9
Code
20 days?Mon 9/12/05Fri 10/7/05 
10
Test & Fix (sev 1 & 2)
5 days?Mon 10/10/05Fri 10/14/05 
11
Test & Fix (sev 3 & 4)
5 days?Mon 10/17/05Fri 10/21/05 
12
Iteration 3
20 days?Mon 10/17/05Fri 11/11/05 
13
Test & Fix (sev 1 & 2)
10 days?Mon 10/17/05Fri 10/28/05 
14
Test & Fix (STOP-SHIPs only)
10 days?Mon 10/31/05Fri 11/11/05 
15
TPTP 4.1 GA
0 daysMon 11/14/05Mon 11/14/05 
   
 
   
 
   