| ID | Task Name | Duration | Start_Date | Finish_Date | Notes |
| 1 | TPTP 3.0.2 | 67.88 days | Mon 1/17/05 | Fri 4/15/05 | http://dev.eclipse.org/viewcvs/index.cgi/%7Echeckout%7E/eclipse-project-home/plans/3_0/freeze_plan_3_0_2.html |
| 2 | Eclipse 3.0.2 RC 1 Driver | 0 days | Thu 2/17/05 | Thu 2/17/05 | |
| 3 | TPTP 3.0.2 RC 1 Driver | 0 days | Fri 2/18/05 | Fri 2/18/05 | |
| 4 | Eclipse 3.0.2 RC 2 Driver | 0 days | Wed 2/23/05 | Wed 2/23/05 | |
| 5 | NL TVT | 30 days | Wed 3/9/05 | Fri 4/15/05 | |
| 6 | NL PII Drop 1 | 0 days | Mon 1/17/05 | Mon 1/17/05 | Translation into Arabic, Czech, Hungarian, Polish, Russian |
| 7 | NL Doc Drop 1 | 0 days | Mon 1/17/05 | Mon 1/17/05 | Translation into Arabic, Czech, Hungarian, Polish, Russian |
| 8 | RC 2 regression test pass | 7 days | Mon 2/28/05 | Tue 3/8/05 | The goal is to verify all the fixes and check for any regressions. |
| 9 | RC 3 driver if eclipse decides to have one | 0 days | Wed 3/9/05 | Wed 3/9/05 | Release candidate 3, if required, to fix problems detected during the test pass. There is no formal test pass for RC3 and beyond, other than a careful check for last minute regressions. |
| 10 | TPTP
3.0.2 GA | 0 days | Fri 3/18/05 | Fri 3/18/05 | |
| 11 | TPTP 3.3/4.0 | 173.88 days? | Mon 1/3/05 | Fri 8/26/05 | |
| 12 | Iteration 1 | 34.88 days | Mon 1/3/05 | Fri 2/18/05 | |
| 13 | Design | 5 days | Mon 1/3/05 | Fri 1/7/05 | |
| 14 | Code | 20 days | Mon 1/10/05 | Fri 2/4/05 | |
| 15 | Test & Fix (sev 1 & 2) | 5 days | Mon 2/7/05 | Fri 2/11/05 | |
| 16 | Fix (sev 3 & 4) | 5 days | Fri 2/11/05 | Fri 2/18/05 | |
| 17 | Iteration 2 | 42.13 days | Fri 2/11/05 | Fri 4/8/05 | |
| 18 | Design | 5 days | Fri 2/11/05 | Fri 2/18/05 | |
| 19 | Code | 24 days | Mon 2/21/05 | Fri 3/25/05 | |
| 20 | Test & Fix (sev 1 & 2) | 5 days | Mon 3/28/05 | Fri 4/1/05 | |
| 21 | Fix (sev 3 & 4) | 5 days | Mon 4/4/05 | Fri 4/8/05 | |
| 22 | API
freeze (both streams) | 0 days | Sun 4/10/05 | Sun 4/10/05 | |
| 23 | Function
freeze that affects Doc & PII (both streams) | 0 days | Sun 4/10/05 | Sun 4/10/05 | |
| 24 | UI
freeze (both streams) | 0 days | Sun 4/10/05 | Sun 4/10/05 | |
| 25 | Iteration 3 | 32 days? | Mon 4/4/05 | Mon 5/16/05 | |
| 26 | Design | 5 days? | Mon 4/4/05 | Fri 4/8/05 | |
| 27 | NL Enablement Test (4.0 stream only) | 31.88 days | Mon 4/4/05 | Fri 5/13/05 | |
| 28 | NL PII Drop 1 (4.0 stream only) | 0 days | Mon 4/18/05 | Mon 4/18/05 | Based on eclipse M6 |
| 29 | Code | 15 days | Mon 4/11/05 | Fri 4/29/05 | |
| 30 | NL drop (PII only) 3.3 stream. This is the only drop. | 0 days | Wed 4/27/05 | Wed 4/27/05 | |
| 31 | Test & Fix (sev 1 & 2) | 5 days | Mon 5/2/05 | Fri 5/6/05 | |
| 32 | TVT
and enablement test cases for 3.3 due | 0 days | Thu 5/5/05 | Thu 5/5/05 | |
| 33 | Fix (sev 3 & 4) | 5 days | Fri 5/6/05 | Fri 5/13/05 | |
| 34 | Doc
freeze (both streams) | 0 days | Mon 5/16/05 | Mon 5/16/05 | |
| 35 | NL PII Return 1 (4.0 only) | 0 days | Mon 5/16/05 | Mon 5/16/05 | |
| 36 | Doc
Drop (3.3 only; this is the only drop) | 0 days | Mon 5/16/05 | Mon 5/16/05 | |
| 37 | TPTP
3.3 GA | 0 days | Mon 5/16/05 | Mon 5/16/05 | |
| 38 | Iteration 4 | 35 days | Fri 5/6/05 | Fri 6/24/05 | |
| 39 | Design | 5 days | Fri 5/6/05 | Fri 5/13/05 | |
| 40 | NL PII Drop 2 (4.0 stream only) | 0 days | Thu 5/19/05 | Thu 5/19/05 | Based on eclipse M7 |
| 41 | NL Doc Drop 1 (4.0 stream only) | 0 days | Thu 5/19/05 | Thu 5/19/05 | Based on eclipse M7 |
| 42 | TVT
test cases for 4.0 due | 0 days | Fri 6/3/05 | Fri 6/3/05 | |
| 43 | Code | 20 days | Fri 5/13/05 | Fri 6/10/05 | |
| 44 | NL PII Drop 3 (4.0 only) | 0 days | Thu 6/9/05 | Thu 6/9/05 | Based on eclipse M7 |
| 45 | NL PII Return 2 (4.0 stream only) | 0 days | Wed 6/15/05 | Wed 6/15/05 | |
| 46 | Test & Fix (sev 1 & 2) | 5 days | Fri 6/10/05 | Fri 6/17/05 | |
| 47 | NL Doc Return 1 (4.0 only) | 0 days | Thu 6/23/05 | Thu 6/23/05 | |
| 48 | Fix (sev 3 & 4) | 5 days | Fri 6/17/05 | Fri 6/24/05 | |
| 49 | TPTP
4.0 GA | 0 days | Mon 6/27/05 | Mon 6/27/05 | |
| 50 | NL PII Return 3 (4.0 only) | 0 days | Wed 6/29/05 | Wed 6/29/05 | |
| 51 | NL PII Drop 4 | 0 days | Thu 6/30/05 | Thu 6/30/05 | For emergencies only. Do not plan on using this drop. Based on eclipse 3.1 GM. Small volume. |
| 52 | NL PII Return 4 | 0 days | Fri 7/8/05 | Fri 7/8/05 | |
| 53 | NL TVT (4.0 stream) | 35 days | Fri 7/8/05 | Fri 8/26/05 | |
| 54 | NL Doc Drop 2 (4.0 only) | 0 days | Thu 7/21/05 | Thu 7/21/05 | Small volume. |
| 55 | NL Doc Return 2 (4.0 only) | 0 days | Fri 8/12/05 | Fri 8/12/05 | |
| 56 | Eclipse 3.1 Milestones | 98 days | Mon 1/3/05 | Fri 5/13/05 | http://eclipse.org/eclipse/development/eclipse_project_plan_3_1.html |
| 57 | Eclipse 3.1 M5 | 0 days | Fri 2/18/05 | Fri 2/18/05 | |
| 58 | Eclipse 3.1 M6 | 0 days | Fri 4/1/05 | Fri 4/1/05 | API complete and API freeze |
| 59 | Eclipse 3.1 M7 | 0 days | Fri 5/13/05 | Fri 5/13/05 | GM, feature complete, development freeze, lock down and testing begins |
| 60 | Eclipse 3.1 GA | 0 days | Mon 1/3/05 | Mon 1/3/05 | Endgame plan: http://dev.eclipse.org/viewcvs/index.cgi/%7Echeckout%7E/eclipse-project-home/plans/3_1/freeze_plan.html |