g-Eclipse Project Plan

Within the g-Eclipse project the following milestones and releases are defined. The project plan for the upcoming g-Eclipse 1.0 release is available in the new format.

Release 1.0.0

Version 1.0.0 is called the mature release and is scheduled for December 2008. The g-Eclipse project plan is available in the standard project plan format.

  • including an implementation for the Amazon S3 and EC2 services
  • revision of the core features
  • final definition of API and extension points

Release 0.5.0

Version 0.5.0 is called the first minor prototype release and is scheduled for September 2007. It contains the following features:

  • Grid authentication management
  • Grid resource management
  • Grid job management
  • Grid data management
  • including an implementation for the gLite middleware.