Resource conflicting rule [message #491592] |
Thu, 15 October 2009 07:34 |
Ravi Messages: 16 Registered: July 2009 |
Junior Member |
|
|
IResource implements ISchedulingRule which has method
isConflicting(IScheduleRule)
The implementation of this method in Resource class has a check to see if
the conflicting rule is an IResource and is prefix of the current IResource
and if so, they are considered to be conflicting.
This is means for every resource in the workspace, the entire workspace is
locked. For example, I am trying say compile a LARGE project and say it
takes about 5 minutes to complete. I would like to work with resources in
the other projects like create/delete/modify resources. Currently it doesn't
allow me if I am running the compile in a job and I specify the project as
the IScheduleRule. Is this a bug? Already reported? Any thoughts/Comments
are appreciated.
Thanks,
Ravi.
|
|
|