I am developing an engineering work process based upon an international
standard. The standard is one PDF document with 100 pages and 300 'shall'
statements. I am looking for details in how to manage this. I have spent
the last two years reading about SE methods and tools. I am now ready to
start practicing.

I have written many engineering work processes but I have never taken this
approach. I am particularly interested in the ability to trace functional
activities back to requirements - assuring that everything is being
addressed and nothing is left out. And the obvious long term ability to
modify the process when future revisions to the standard are published.

I would appreciate all comments.

Thanks,
Ray
Re: Detailing Requirements [message #12477 is a reply to message #11867] Thu, 26 March 2009 20:55 Go to previous messageGo to next message
Ryan D. Brooks is currently offline Ryan D. BrooksFriend
Messages: 100
Registered: July 2009
Senior Member
Hi Ray,

One typical approach for importing a large document (specification,
standard, requirements, process, etc.) into OSEE is to make each paragraph
a separate artifact. One option to do this automatically is to import an
existing Word 2003 XML document. The Word styles "Heading (1...9)" are
used to determine the breakout into individual artifacts and their
position in the document hierarchy.

It is also typical to create a functional decomposition using "Component"
artifacts in the artifact explorer. Then to allocation (through the
allocation relation) the requirements to the components.

Then BLAM can be used to generate the traceability reports needed to look
for holes in the allocation.

Regards,
Ryan


Thanks,
Ryan Brooks
Re: Detailing Requirements [message #12498 is a reply to message #12477] Fri, 27 March 2009 03:53 Go to previous message
Ray Joseph is currently offline Ray JosephFriend
Messages: 87
Registered: July 2009
Member
Ryan,

That sounds straight forward. I'll give it a try.

Thank you,
Ray
Re: Detailing Requirements [message #572417 is a reply to message #11867] Thu, 26 March 2009 20:55 Go to previous message
Ryan D. Brooks is currently offline Ryan D. BrooksFriend
Messages: 100
Registered: July 2009
Senior Member
Hi Ray,

One typical approach for importing a large document (specification,
standard, requirements, process, etc.) into OSEE is to make each paragraph
a separate artifact. One option to do this automatically is to import an
existing Word 2003 XML document. The Word styles "Heading (1...9)" are
used to determine the breakout into individual artifacts and their
position in the document hierarchy.

It is also typical to create a functional decomposition using "Component"
artifacts in the artifact explorer. Then to allocation (through the
allocation relation) the requirements to the components.

Then BLAM can be used to generate the traceability reports needed to look
for holes in the allocation.

Regards,
Ryan


Thanks,
Ryan Brooks
Re: Detailing Requirements [message #572437 is a reply to message #12477] Fri, 27 March 2009 03:53 Go to previous message
Ray Joseph is currently offline Ray JosephFriend
Messages: 87
Registered: July 2009
Member
Ryan,

That sounds straight forward. I'll give it a try.

Thank you,
Ray
Previous Topic:Installation Help - Two Plug-ins?
Next Topic:User getting started
Goto Forum:
  


Current Time: Thu Mar 28 22:25:50 GMT 2024

Powered by FUDForum. Page generated in 0.03154 seconds
.:: Contact :: Home ::.

Powered by: FUDforum 3.0.2.
Copyright ©2001-2010 FUDforum Bulletin Board Software

Back to the top