ServiceTask should have only one incoming connection. [message #1847788] Mon, 08 November 2021 07:04 Go to next message
Eclipse UserFriend
Consider a business process where task A branches off to task B1 and task B2. But, outcome of B1 and B2 is to be processed by task C. The BPMN modeler raises an error if I put sequence flows from B1 and B2 into C. The only way to get around this is to create C1 and C2. This will make my BPMN model verbose.

1. Why does such a restriction exist? I noticed the same for EndEvent too.
2. What is the work around, recommended approach for such "diamond" flows?
Re: ServiceTask should have only one incoming connection. [message #1847799 is a reply to message #1847788] Mon, 08 November 2021 13:44 Go to previous messageGo to next message
Eclipse UserFriend
You can allow multiple connections setting the option in the BPMN 2.0 preferences

index.php/fa/41282/0/



Re: ServiceTask should have only one incoming connection. [message #1847805 is a reply to message #1847799] Mon, 08 November 2021 19:10 Go to previous message
Eclipse UserFriend
Thank you. That helped!
Previous Topic:Migrating Eclipse BPMN2 Modeler to web
Next Topic:Exporting BPMN diagram to SVG
Goto Forum:
  


Current Time: Sat Apr 19 15:02:22 EDT 2025

Powered by FUDForum. Page generated in 0.03950 seconds
.:: Contact :: Home ::.

Powered by: FUDforum 3.0.2.
Copyright ©2001-2010 FUDforum Bulletin Board Software

Back to the top