Project Status as of M1 date [message #3216] Mon, 20 February 2006 22:30 Go to next message
Kevin McGuire is currently offline Kevin McGuireFriend
Messages: 3
Registered: July 2009
Junior Member
Hi gang,

In the spirit of good open source participation I thought I should log
our collective status vis-a-vis the plan.

Summary:
---------

We are midway through M2 with some code working (can open a process) but
some important design work remains uncompleted (actually, not even
started). This is a concern as downstream coding work was dependent on
this.

On the bright side, with some more effort we should be able to get to
the M2 goal of being able to create a simple BPEL process and do some
editing of it.

We've had some startup hickups but I am optimistic that as more
resources are applied we can get ourselves back on track.

We should have a status call come M2 completion and determine what
action should be taken. As we are not on plan, and realistically can't
get back on plan by then, we need to consider whether a catchup can
occur to put us back on track for M3 or if schedule adjustments are
required.


Itemized list from the plan:
----------------------------

==M0: Dec 15==
Document and share existing extension points (IBM) - Done
Create list of default implementation to create (Oracle) - Done
Feedback on extension points (Oracle) - Done
Start implementation of default extension points (Oracle) - Not started
Start WSDL and Partner Link discussion (Oracle/IBM) - IBM to investigate
extensibility of WTP WSDL editor
Storyboard for building LoanFlow (Oracle/IBM) - Not started
Start Runtime/Debugger API design (Oracle) - Not started
Definition of process to open and display in M1 (Oracle/IBM) - Done,
agreed on OASIS example plus simple example
Legal resolution (IBM/Oracle) - Done
Define the list of samples for M1 (Oracle/IBM) - Not started

==M1: View Only. January 31==
Contribute source (Pending approvals) (IBM) - Done
Ability to open and display a BPEL process, not necessarily edit or
author (IBM) - Done
Design of Validation Framework (Oracle) - Not started
Define list of validation errors/warnings with strings (Oracle) - Not
started
Define what "simple" and "complex" are based on Storyboard (Oracle/IBM)
- Not started
Plan for final artwork (Oracle/IBM) - Not started
Contribute samples (Oracle/IBM) - Not done

==M2: View and Author simple, exercise extension points. March 7==
Implement default, simple set of UI extensions (prompters, XPath editor
etc.) (Oracle) - Not started
Finish enough implementation so that we can create project and build
simple BPEL process (Oracle) - Not started

--------------

Cheers,
Kevin McGuire
Re: Project Status as of M1 date [message #3647 is a reply to message #3216] Tue, 14 March 2006 17:27 Go to previous message
Greg Adams is currently offline Greg AdamsFriend
Messages: 5
Registered: July 2009
Junior Member
Kevin,
Since we have cleared M2 (based on posted schedule) I wanted to focus on
what we missed based on your note.

> ==M1: View Only. January 31==
Design of Validation Framework
Oracle
Define list of validation errors/warnings with strings
Oracle
Define what "simple" and "complex" are based on Storyboard
Oracle/IBM
Plan for final artwork
Oracle/IBM
Contribute samples
Oracle/IBM

==M2: View and Author simple, exercise extension points. March 7==
Implement default, simple set of UI extensions (prompters, XPath editor
etc.) Oracle
Finish enough implementation so that we can create project and build
simple BPEL process Oracle


GOING FORWARD
==================
Is there a planned call to review :
- progress
- future milestone impact
- identifying committed dates when the above missed items will be
available - imho we should not do M3 until we have all the missing parts of
M1 and M2.
- participation by current members
- potential participation by new people who have expressed an interest

Seems like this is a good time to do it?


/Greg


"Kevin McGuire" <kevin_mcguire@ca.ibm.com> wrote in message
news:dtdfts$6q6$1@utils.eclipse.org...
> Hi gang,
>
> In the spirit of good open source participation I thought I should log
> our collective status vis-a-vis the plan.
>
> Summary:
> ---------
>
> We are midway through M2 with some code working (can open a process) but
> some important design work remains uncompleted (actually, not even
> started). This is a concern as downstream coding work was dependent on
> this.
>
> On the bright side, with some more effort we should be able to get to
> the M2 goal of being able to create a simple BPEL process and do some
> editing of it.
>
> We've had some startup hickups but I am optimistic that as more
> resources are applied we can get ourselves back on track.
>
> We should have a status call come M2 completion and determine what
> action should be taken. As we are not on plan, and realistically can't
> get back on plan by then, we need to consider whether a catchup can
> occur to put us back on track for M3 or if schedule adjustments are
> required.
>
>
> Itemized list from the plan:
> ----------------------------
>
> ==M0: Dec 15==
> Document and share existing extension points (IBM) - Done
> Create list of default implementation to create (Oracle) - Done
> Feedback on extension points (Oracle) - Done
> Start implementation of default extension points (Oracle) - Not started
> Start WSDL and Partner Link discussion (Oracle/IBM) - IBM to investigate
> extensibility of WTP WSDL editor
> Storyboard for building LoanFlow (Oracle/IBM) - Not started
> Start Runtime/Debugger API design (Oracle) - Not started
> Definition of process to open and display in M1 (Oracle/IBM) - Done,
> agreed on OASIS example plus simple example
> Legal resolution (IBM/Oracle) - Done
> Define the list of samples for M1 (Oracle/IBM) - Not started
>
> ==M1: View Only. January 31==
> Contribute source (Pending approvals) (IBM) - Done
> Ability to open and display a BPEL process, not necessarily edit or
> author (IBM) - Done
> Design of Validation Framework (Oracle) - Not started
> Define list of validation errors/warnings with strings (Oracle) - Not
> started
> Define what "simple" and "complex" are based on Storyboard (Oracle/IBM)
> - Not started
> Plan for final artwork (Oracle/IBM) - Not started
> Contribute samples (Oracle/IBM) - Not done
>
> ==M2: View and Author simple, exercise extension points. March 7==
> Implement default, simple set of UI extensions (prompters, XPath editor
> etc.) (Oracle) - Not started
> Finish enough implementation so that we can create project and build
> simple BPEL process (Oracle) - Not started
>
> --------------
>
> Cheers,
> Kevin McGuire
Previous Topic:BPEL-Editor in RCP app - dependencies?
Next Topic:Moved to M5 builds
Goto Forum:
  


Current Time: Tue Apr 23 12:52:03 GMT 2024

Powered by FUDForum. Page generated in 0.02538 seconds
.:: Contact :: Home ::.

Powered by: FUDforum 3.0.2.
Copyright ©2001-2010 FUDforum Bulletin Board Software

Back to the top