Action items at the end.
Attendees
---------
- Gerry, Abhi, Jeff, Valery, Brian, Mike,
Dale, Jim, Tom, Heather, Daniel, Duane, Mary
AGENDA
======
IIW preparations
–
Significant progress had been made on the demo since
last week.
–
Have
succeeded in doing demonstrating end-to-end multi-project interoperability using
IE7, Higgins and Bandit to login to a CardSpace enabled site.
-
Still have server issues for hosting the STS and IdAS
– are implementing plan B
-
Testing with other projects has begun.
o Jeff has been able to
successfully test CA's eTrust Directory against the latest IdAS JUnit test
bed. IdAS was able to bind, read the schema, and access the directories
contents. The tests ran successfully within an eclipse project, and
exercise the basic binding mechanisms. He hopes to get to the next level
of verification when and if additional unit tests are available.
o Chuck Mortimore is
beginning to test his ISS with Higgins
Other topics
------------
- Higgins
has a virtual Eclipse Server to run our STS – we will make it available as
soon as we have it up and running.
- EclipseCON
–
Brian and Mike have discussed proposing an
ALF-Higgins STS demo for EclipseCON.
Demo proposals aren’t due until next year.
–
Long talk proposals are due December 1. So far there are three presentation
proposals mentioning Higgins – Eclipsezilla numbers 3694, 3764 and 3765. Voting and comments on presentations can
be done through December 1.
-
Novell has generously offered to host the next
Higgins face-to-face meeting in Provo January 24-26
-
Gerry has made the first pass on an outline for the “Principles
of Identity” paper. He and
Mary plan to iterate on it and distribute a preliminary draft outline to the other
volunteers: (Paul, Tony, Dale, Tom,
Jeff) on Friday afternoon. Eve has
also offered to review it.
-
Process for third party IP with IPzilla - Mary to review
Tom’s updates to the wiki.
-
Oracle announcement on Identity Governance framework
and its Higgins messaging. Are
scheduling follow-up with Oracle.
Action Items
============
- IIW Demo
team: Finish demo preparations and Messaging for IIW. Have pre-meeting as soon as Dale arrives
at IIW
- Dale,
Mary, Paul: meet with Oracle at IIW – will need to be Monday or Tuesday
evening due to Uppili’s schedule
- Jeff and
Mary to distribute draft positing paper outline Friday.
- Mary: Next
steps on third party IP pages of the wiki