Project Plan For technology.epf, version 1.5.1.6
Introduction
The approach for this project plan will be discussed at the Thurs May 9, 2013 EPF meeting. This is planned to be just a bug fix release, and will be made available on Nov 1, 2013.
Release Deliverables
Deliverables include installable EPF composer build and the EPF practices library. The release work also includes updating the EPF web site with download bits, published, release notes, and updates to the EPF Wiki.
Release Milestones
| M1 | 02/28/2013 | |
| M2 | 03/31/2013 | |
| M3 | 04/30/2013 | |
| M4 | 05/31/2013 | |
| M5 | 06/30/2013 | |
| M6 | 07/31/2013 | |
| M7 | 08/30/2013 | |
| M8 | 09/31/2013 | |
| M9 | 10/30/2013 |
Target Environments
Win32 and Linux
Internationalization
None
Compatibility with Previous Releases
No incompatibilities have been introduced.
Themes and Priorities
EPF Composer tooling capabilities
- Bug fixes only.
- Refactoring of EPF plug-ins so that it can be run as headless application without UI dependency [400249] (target milestone: 1.5.1.6 M2)
EPF Practices library
- Scrum plug-in will be made compatible with the EPF Practices Library, plus bug fixes and minor content updates.