Project Plan For Riena Project, version 5.0

Introduction

This plan describes the work for Riena 5.0.0, which is planned for Jun 2013 (Kepler release train). Riena 5.0. is a major release. One of the targets is to make Riena ready to run on top of e4.

Release Deliverables

Riena 5.0 runs on Eclipse 3.x, Eclipse 4.x and on RAP 2.1. Main deliverable is the ability to run on e4 and RAP 2.1 and bug fixing, stabilizing, reducing the number of P2 bugs in bugzilla.

Table of Contents

Release Milestones

Riena plans on delivering milestone on the following schedule:
M4December 21, 2012
M5February 8, 2013
M6March 22, 2013
(API Freeze)
M7May 10, 2013
(Feature Freeze)

Riena 5.0 will be released on June 26, 2013, together with Eclipse Kepler.

Table of Contents

Target Environments

Riena's target environments are:
  • Eclipse-based RCP 4.3/3.8 Applications
  • Eclipse-based RAP 2.1(Web) Applications
  • Equinox-Based Runtimes (e.g. Equinox servers)

Internationalization

Riena uses Eclipse internationalization support whereever it applies for its own components

Table of Contents

Compatibility with Previous Releases

Riena's APIs are currently stable. We intend to improve and break few APIs on the way to the 5.0 release. API are considered all exported packages that are not marked as

x-internal:=true
in their Export-Package declaration.

Table of Contents

view raw xml of project plan
from project meta-data key "projectplanurl"