Project Plan For Webtools Releng, version 3.1
Introduction
The release engineering (releng) project provides builds and test frameworks for WTP.
Release Deliverables
- the Builder
- JUnit test framework
- performance test
- API tests
Release Milestones
WTP Milestones follow the Eclipse release milestones by an offset of 2 as set by the Galileo release schedule.
M1 | 8/31/2008 | M1 milestone |
M2 | 10/01/2008 | M2 milestone. |
M3 | 11/12/2008 | M3 milestone |
M4 | 12/29/2008 | M4 milestone |
M5 | 2/06/2009 | M5 milestone |
M6 | 3/12/2009 | M6 milestone.Feature complete, API and UI Freeze |
M7 | 5/05/2009 | M7 milestone. PMC review starts |
RC1 | 5/19/2009 | RC1 milestone.PMC approval required, 1 vote required |
RC2 | 5/26/2009 | RC2 milestone.PMC approval required, 2 votes required |
RC3 | 6/02/2009 | RC3 milestone.Document Freeze. PMC approval required, 3 votes required |
RC4 | 6/09/2009 | RC4 milestone.Only stop-ship defects, PMC approval required, 3 vote required |
RC5 | 6/16/2009 | RC5 milestone.Only stop-ship defects, PMC approval required, 3 vote required |
GA | 6/26/2009 | GA |
Target Environments
WTP builds support only the Linux environment (though some have requested effort be put into supporting windows as well).
.
Internationalization
Internationalization and Localization will be supported.
-
Internationalization (I18N)
Each project should be able to work in an international environment, including support for operating in different locales and processing/displaying international data (dates, strings, etc.).
-
Localization
Each project should provide an environment that supports the localization of the technology (i.e. translation). This includes, but is not limited to, ensuring that strings are externalized for easy translation.
Where possible, projects should use an open and transparent process to create, maintain and deliver language packs translated into multiple languages in a timely manner. The primary languages to consider are: English, Simplified Chinese, Traditional Chinese, Japanese, French, German, Spanish.
Compatibility with Previous Releases
Themes and Priorities
Themes and their priorities communicate the main objectives of the project and their importance. The following themes are derived from those defined by the Eclipse Requirement council for the Eclipse Galileo release and from the WTP 3.0 release themes. These will be prioritized based on the community feedback. New themes could be synthesized from the requirements submitted by the community.
The sections to follow defines the plan items in the Server Tools project. The plan items are grouped under the respective themes where applicable. Each plan item corresponds to a new feature, API or some apsects of the project that needs to be improved. A plan item has an entry in the Eclipse Bugzilla system that has a detailed description of the plan item. Not all plan items represent the same amount of work; some may be quite large, others, quite small. Although some plan items are for work that is more pressing than others, the plan items appear in no particular order. See the corresponding bugzilla items for up-to-date status information on ongoing work and planned delivery milestones.
Other
Following are plan items that are not yet categorized into a theme.
- Committed
- Create separate build/distributions for the Faceted Project Framework [200247]
(target milestone: 3.1 M3)
- Create separate build/distributions for the Faceted Project Framework [200247]
- Proposed
- Deferred
- [releng] WTP should move the capability definitions from the runtime component to a higher one [139778] (target milestone: Future)
Appendix References
- The general WTP plan can be found here.