Synchronization of fix version updated JIRA tasks [message #64501] Tue, 20 January 2009 10:27 Go to next message
Eric TOURNIER is currently offline Eric TOURNIERFriend
Messages: 2
Registered: July 2009
Junior Member
Hi :)

Before posting to the Mylyn team, I would like to know if the following
is a bug :) Here are the differents steps :

1- A JIRA task is updated on the JIRA server : precisely a new version is
added to the project and the fix version of the task is modified to be now
the newly added version. For example, there were 2 initial versions (2.2.3
and 2.5), version 2.4 is added and the fix version of TASK-XXX is moved
from 2.5 to 2.4 ;

2- On Mylyn/Eclipse, TASK-XXX is opened. Fix versions listbox (Attributes
section) contains 2.2.3 and 2.5 values. Then TASK-XXX is synchronized
(F5). The link "Task has incoming changes" appears ;

3- Clicking on the link does not modify Fix versions listbox which still
contains 2.2.3 and 2.5 values ;

4- Every time the Synchronize action is done, link "Task has incoming
changes" appears even if no modification on the JIRA has been done.

It looks like a bug but did someone face this before ?

Thanks in advance for your help and your advices
Eric
Re: Synchronization of fix version updated JIRA tasks [message #64524 is a reply to message #64501] Tue, 20 January 2009 10:40 Go to previous message
Jorrit Schippers is currently offline Jorrit SchippersFriend
Messages: 26
Registered: July 2009
Junior Member
Eric TOURNIER wrote:
> Hi :)
>
> Before posting to the Mylyn team, I would like to know if the following
> is a bug :) Here are the differents steps :
>
> 1- A JIRA task is updated on the JIRA server : precisely a new version
> is added to the project and the fix version of the task is modified to
> be now the newly added version. For example, there were 2 initial
> versions (2.2.3 and 2.5), version 2.4 is added and the fix version of
> TASK-XXX is moved from 2.5 to 2.4 ;
>
> 2- On Mylyn/Eclipse, TASK-XXX is opened. Fix versions listbox
> (Attributes section) contains 2.2.3 and 2.5 values. Then TASK-XXX is
> synchronized (F5). The link "Task has incoming changes" appears ;
>
> 3- Clicking on the link does not modify Fix versions listbox which still
> contains 2.2.3 and 2.5 values ;
>
> 4- Every time the Synchronize action is done, link "Task has incoming
> changes" appears even if no modification on the JIRA has been done.
>
> It looks like a bug but did someone face this before ?
>
> Thanks in advance for your help and your advices
> Eric
>


You can update the server values by going to the query definition window
and clicking the appropriate button (at least for trac and bugzilla).
Does it work then?

Perhaps a new feature for Mylyn could be that new server values are
retrieved automatically when it encounters an unknown value during
synchronization. Mylyn could also display a friendly dialog explaining
that it had encountered unknown value and asks if the values should be
updated from the repository. This dialog should contain a checkbox to
disable the dialog, because maybe some bad configured repository causes
tasks to be sent out with unknown properties that can never be retrieved.

--
Jorrit
Re: Synchronization of fix version updated JIRA tasks [message #595871 is a reply to message #64501] Tue, 20 January 2009 10:40 Go to previous message
Jorrit Schippers is currently offline Jorrit SchippersFriend
Messages: 26
Registered: July 2009
Junior Member
Eric TOURNIER wrote:
> Hi :)
>
> Before posting to the Mylyn team, I would like to know if the following
> is a bug :) Here are the differents steps :
>
> 1- A JIRA task is updated on the JIRA server : precisely a new version
> is added to the project and the fix version of the task is modified to
> be now the newly added version. For example, there were 2 initial
> versions (2.2.3 and 2.5), version 2.4 is added and the fix version of
> TASK-XXX is moved from 2.5 to 2.4 ;
>
> 2- On Mylyn/Eclipse, TASK-XXX is opened. Fix versions listbox
> (Attributes section) contains 2.2.3 and 2.5 values. Then TASK-XXX is
> synchronized (F5). The link "Task has incoming changes" appears ;
>
> 3- Clicking on the link does not modify Fix versions listbox which still
> contains 2.2.3 and 2.5 values ;
>
> 4- Every time the Synchronize action is done, link "Task has incoming
> changes" appears even if no modification on the JIRA has been done.
>
> It looks like a bug but did someone face this before ?
>
> Thanks in advance for your help and your advices
> Eric
>


You can update the server values by going to the query definition window
and clicking the appropriate button (at least for trac and bugzilla).
Does it work then?

Perhaps a new feature for Mylyn could be that new server values are
retrieved automatically when it encounters an unknown value during
synchronization. Mylyn could also display a friendly dialog explaining
that it had encountered unknown value and asks if the values should be
updated from the repository. This dialog should contain a checkbox to
disable the dialog, because maybe some bad configured repository causes
tasks to be sent out with unknown properties that can never be retrieved.

--
Jorrit
Previous Topic:Possible feature request
Next Topic:How to query only one bug from eclipse's bugzilla
Goto Forum:
  


Current Time: Thu Apr 18 11:52:44 GMT 2024

Powered by FUDForum. Page generated in 0.02548 seconds
.:: Contact :: Home ::.

Powered by: FUDforum 3.0.2.
Copyright ©2001-2010 FUDforum Bulletin Board Software

Back to the top